UMP’s project management

UMP's project management expertise maximises efficiency and minimises risk. We handle all the essential elements – scheduling, cost control, procurement, expediting, commissioning – using MS Projects and MS Teams to keep you informed every step of the way. Focus on...

Partner with UMP for custom-built process plants

Partner with UMP for custom-built process plants, machines, and assemblies. Our engineering and fabrication expertise ensures high-quality manufacturing and seamless integration for OEMs globally. Learn more about our custom manufacturing capabilities:...

global OEMs

Global OEMs

Global OEMs UMP's engineering and fabrication division provides custom-built solutions for global OEMs while offering flexible subcontracting services for a variety of industries. From design to delivery, we're your one-stop shop for precision manufacturing. Learn...

Our Latest Publication

Jorf Lasfar Slurry Pipeline Project, Morocco

UMP was featured in the SAICE–SAFCEC 2015 AWARDS profile

 

Client Testimonial

We are soon approaching the structural erection and mechanical installation completion for CV15 & CV16 Bogatyr Coal Sampling Plants in Kazakhstan. The erection & mechanical installation has been somewhat of an uneventful exercise with very few interface challenges and good comments from both the installation company on site, as well as our client and ultimately the end user.

 As we know, manufacturing started in November 2020 (a month late due to unforeseen circumstances), with a delivery date 1st week March 2021 – given the scope of the project, a very tall order even without the global challenges inflicted by Covid19. Thanks to the unwavering efforts by team UMP, we were able to commence a staggered delivery starting end of February 2021, with final machine and parts delivery end of March 2021 despite starting a month late through no fault of UMP.

Manufacturing and final product quality has been exceptional, project management to be proud of and over-all project execution second to none!

I would like to send out mine and ultimately Thermo Fisher Scientific’s gratitude! Without UMP this project would not have become a reality let alone where we are now with successful installation and on the cusp of commissioning.

Thermo will benefit for many years due to the spares and parts orders this project will generate – I believe UMP will reap the same.”

Stephen Labram

Snr Project Engineer – South Africa

Thermo Fisher Scientific